| Concrete
Pavement Project Detail |
| Project |
: The Siam Romanee Road Project
|
| Location |
: Charernkrung Road, Ratanakosin
Island, Bangkok |
| Project Description |
: Renolith Course with Concrete
Pavement |
| Total Area |
: 2,000 m2 |
| Type of Existing Soil |
: Silty Soft Clay |
| Type of Soil to Fill |
: Imported Laterite for Sub-grade
Course |
| Type of Soil for Renolith
Course |
: Imported Laterite for Renolith
Course |
| Typical Section |
: Sub-grade Thickness 10
cm |
|
: Renolith Course Thickness
10 cm |
|
: Concrete Pavement Thickness
3 cm |
| Mix Design of Renolith
Course |
: - Portland Cement 7 % by
Weight of Dry Soil |
|
- Renolith 5 % by Weight
of Portland Cement |
|
- Water 10 % by Weight of
Dry Soil |
| Equipment |
: Back-Hoe D-2 Tractor Roller
Compactor |
| Construction Period |
: 7 Days, November 1999 |
| Project Cost |
: 1,000,000 Baht |
| Process |
: - Clearing the construction
site, then importing the laterite to |
|
fill in, and compacting
through the area |
|
- Mixing laterite with Portland
cement, then spraying Renolith |
|
and water on the prepared
materials, then compacting to |
|
the dry density
not less than 95% maximum dry density |
|
- Casting concrete pavement |
| Note |
: - Restriction of working
condition |
|
- High residential area
|
|
- High cost of transporting
the selected material. |
|
- Very soft soil foundation |
|
|
|
|