| Project Detail |
| Project |
: Queen Sirikit Health Park |
|
Managed by Mahsarakarm Municipal |
| Location |
: Mahasarakham Province |
| Project Description |
:
Lining to Protect Permeability of Water |
| Total Area |
: 625 m2 |
| Type of Existing Soil |
: Sandy Silt |
| Type of Soil to Fill |
: No Fill |
| Type of Soil for Renolith Course |
: Existing Soil |
| Typical Section |
: Renolith Slab Thickness 20 cm |
|
: Renolith Retaining Wall Thickness 15 cm |
| Mix Design of Renolith Course |
: - Cement 5% by Weight of Dry Soil |
|
- Renolith 5% by Weight of Cement |
|
- Water 10% by Weight of Dry Soil |
| Equipment |
: Tilting Concrete Mixer |
| Construction Period |
: 31 August-8 September,1999 |
| Project Cost |
: 82,000 Baht |
| Process |
: - Shaping the pond and leveling the base and retaining |
|
wall area of the pond |
|
- Mixing soil, cement, Renolith and water in tilting |
|
concrete mixer |
|
- Casting slab and lining through the pond |
|
|