| Road and Car Parking Project Detail |
| Project |
: Number One Driving Range |
| Location |
: Pracha-U-Thit Road, Bangkok |
| Project Description |
: Muddy Pond Lining for servicing and preventing of golf |
|
: balls lost in the mud |
| Total Area |
: 1,000 m2 |
| Type of Existing Soil |
: Muddy soft clay |
| Type of Soil to Fill |
: No Fill |
| Type of Soil for Renolith Course |
: Existing Soil |
| Typical Section |
: Renolith Course Stabilisation With 20 cm Thickness |
|
: Concrete Pavement With 5 cm Thickness |
| Mix Design of Renolith Course |
: - Cement 10 % by Weight of Dry Soil |
|
- Renolith 10 % by Weight of Cement |
|
- Water varies percentage depended on soil condition |
| Equipment |
: Tilting Concrete Mixer |
| Construction Period |
: 5 Days, February 1999 |
| Project Cost |
: 500,000 Baht |
| Process |
: - Shaping the pond and leveling the base and retaining |
|
wall area of the pond |
|
- Mixing soil, cement, Renolith and water in tilting |
|
concrete mixer |
|
- Casting slab and lining through the pond |
|
|