| Road
Construction Project Detail |
| Project |
: Renolith Farm Road Construction |
| Location |
: Jitra, Kedah State, Malaysia |
| Project Description |
: Renolith Soil Cement Road
Base Construction |
| Total Area |
: 4.30 m. x 3,240 m. |
| Type of Existing Soil |
: Laterite |
| Type of Soil to Fill |
: White Laterite ( A-7-5,
AASHO Classification ) |
| Type of Soil for Renolith
Course |
: White Laterite ( A-7-5,
AASHO Classification ) |
| Typical Section |
: Renolith Course Thickness
15 cm |
| Mix Design of Renolith
Course |
: - Portland Cement 6.8
% by Weight of Dry Soil |
|
- Renolith 5 % by Weight
of Portland Cement |
|
- Water 8 % by Weight of
Dry Soil |
| Equipment |
: Grader |
|
Rotary Tiller |
|
Compactor |
|
Water Tank |
| Construction length per
1 day |
: 300 - 400 m. |
| Mainpower |
: 10 males |
| Process |
: - Grading and scarifying
the construction area. |
|
- Spreading Portland cement
on the work area. |
|
- Homogeneously mixing Portland
cement to the soil. |
|
- Mixing Renolith
with water and then spraying on the prepared area |
|
- Homogeneously
mixing Renolith and soil - cement, |
|
then compacting. |
|
|
|
|